Overnight Chiller Installation for Hospital Theatre Suite
Challenge
All Seasons Hire received a call late on a Friday afternoon from a North London Hospital Estates Manager. A refrigeration contractor had been working all day on critical chilled water system which provided cooling for a suite of theatres. The Hospital were looking at the unthinkable; several days of cancelled operations.
An All Seasons Hire technical engineering manager attended the site that evening and designed a way to connect a temporary chiller into the existing building infrastructure. A price was agreed and immediately the team swung into action. Engineers modified the sites pipe work overnight and the chiller arrived Saturday morning for installation.
Solution
On Site survey within 2 hours to understand and create a project plan to deliver and install a Chiller within 24 hours
A four man team working overnight to minimise down time
500kW chiller delivered, lifted and installed the next morning
The chiller was connected into the existing system to minimise disruption
Wide range of HVAC equipment to suit all NHS applications
Benefits
Full turnkey solution to reduce lead-time and minimise down time
Highly experienced installation team, worked through the night to ensure that system was ready for connection next day
Nationwide fast response times ensure mission critical equipment is kept operational
24/7 availability giving unparalleled levels of support to the NHS